Meshtastic LongFast, LongTurbo and the FCC: Nearly a Month Later

Research checked October 14, 2026. A follow-up to our September 19 LongFast and FCC discussion.

Nearly a month later, we have more to work with than forum speculation: an official Meshtastic explanation, a replacement for a revoked firmware release, and a detailed field report from a community running a 500 kHz mesh. The useful question is no longer just “Why is the default changing?” It is “How do we make informed decisions without disconnecting our neighbors?”

The biggest update: Meshtastic has explained the change

In its October 8 announcement, Meshtastic explicitly connects the U.S. LongTurbo default to the bandwidth requirement in FCC § 15.247. It also clarifies the scope: the change applies when the U.S. region is selected for the first time on the device’s own screen. An ordinary upgrade does not automatically change an existing node’s preset.

That distinction matters. “New default” does not mean every radio in your area has moved. It also does not mean every setup method behaves identically.

The same announcement warns that 2.8.0 has been revoked because of a packet-signing problem. The replacement, 2.8.1.8e6a88d, released October 1, is still an alpha. Meshtastic advises most users to wait rather than deploy it widely; people already running the revoked 2.8.0 should follow the project’s replacement guidance.

This is not a recommendation to mass-flash unattended mountaintop nodes. A firmware safety fix and a coordinated radio-preset transition are two different jobs.

The FCC question still needs precise wording

47 CFR § 15.247(a)(2) specifies a minimum 6 dB bandwidth of 500 kHz for systems operating under its digital-modulation provision. LongFast’s nominal bandwidth is 250 kHz; LongTurbo’s is 500 kHz.

The important qualification is operating under that provision. This is an existing rule, not evidence of a new LongFast-specific FCC ban this month. Nor is selecting a 500 kHz menu option a complete compliance assessment: measured emissions, power, antenna configuration, and the equipment’s authorization still matter.

Section 15.249 provides a different, field-strength-limited route. It is not a blanket exemption for any LongFast setup, and simply reducing an app’s power setting does not establish compliance. Ask your hardware manufacturer which configuration its documentation supports.

Does 500 kHz mean the mesh will stop working?

A useful counterpoint comes from Calgary. In YYCMesh’s first-hand field report, operators describe months of usable regional communication with more than 300 nodes visible on the public channel.

There is an important detail behind that headline: their setup uses 500 kHz bandwidth and spreading factor 11, but a different coding rate and frequency placement from the standard LongTurbo arrangement. They also improved infrastructure, antenna placement, and traffic management.

The authors explicitly say this was not a controlled comparison. Their results do not prove that changing bandwidth alone improves performance, nor that Calgary’s configuration should be copied into a U.S. deployment. Canada has a different regulator.

Our takeaway: neither “500 kHz ruins every mesh” nor “LongTurbo fixes everything” is supported by that report. Network design and local conditions deserve more attention than preset loyalties.

A quiet radio may be on the wrong mesh

Meshtastic’s radio documentation confirms that LongFast and LongTurbo do not hear each other. A matching channel name alone is not enough: modem settings, frequency, and the appropriate channel key must also match. The channel configuration guide explains why adding another chat channel does not make a single radio operate on two modem presets simultaneously.

This is already a practical onboarding issue. At the time of this review, MeshNY’s own guide describes a small LongTurbo network and a legacy LongFast network alongside its primary network. That is a New York City example, not an Adirondack coverage report or a statewide migration announcement.

If a newly configured radio seems isolated, check its actual settings and ask nearby operators what they use before assuming the antenna is faulty or the local mesh has disappeared. Any transmitting configuration should also be supported by the hardware’s compliance documentation.

What makes sense for Adirondack operators now?

This update is not an ADKMesh cutover announcement. Our recommendation is to prepare a documented, recoverable transition rather than make disconnected changes one radio at a time:

  • Inventory first. Record firmware version, hardware model, region, preset, frequency, antenna, and power configuration. Keep private channel keys out of public screenshots.
  • Separate firmware maintenance from network migration. Export configuration before a supported update, and keep physical recovery possible. Do not leave a node on a release the project has revoked.
  • Use a small, coordinated test group. Choose manufacturer-supported settings and a defined test window. Avoid changing a shared relay without notifying the people who depend on it.
  • Measure delivery, not just discovery. Record messages sent and received, acknowledgments, delay, signal readings, and channel activity across repeatable routes. A long node list is not a delivery-success measurement.
  • Publish the plan before a cutover. Specify the target settings, timing, recovery procedure, and how newcomers can get help.

For Adirondack testing, include obstructed valley paths and ordinary handheld use—not just a favorable summit-to-summit contact. Treat another region’s success as a reason to test carefully, not as a promise about local coverage.

The bottom line: the official explanation is clearer, the firmware warning deserves attention, and useful field experience is emerging. The next step is better coordination and measured local results—not panic, a protocol turf war, or an unannounced network-wide switch.

Have local LongTurbo observations to share? Include your hardware, firmware, approximate terrain, settings, and test method in a comment. Please do not post private keys or exact locations of sensitive installations.

This is a community news and engineering overview, not legal advice or an FCC equipment certification. Release status and regional configurations can change; check the linked primary sources before acting.